Advocate Bibikar & Associates
You have strong grounds to recover your ₹10,00,000 with interest due to the unilateral cancellation of the shop agreement, unauthorized shift to a flat, no Banakhat, delayed possession, and incomplete construction as of 2026. Payment proofs and correspondence bolster your case under Indian laws like RERA (if applicable), Consumer Protection Act, and Contract Act.
File under RERA (TS-RERA for Zahirabad): Demand refund with interest (typically 10-11% p.a.) for delay beyond promised date; project takeover possible if stalled. High success in Telangana cases for delays/non-registration.
Civil Suit: Specific performance or damages under Specific Relief Act; interest via Sec. 73 Contract Act.
Consumer Court: Claim deficiency in service; parallel to RERA, no bar.
Excellent chances of success given proofs and precedents ordering refunds post-delay. Builder’s post-sale refund condition invalid; refuse backdated draft. Act within 2 years of cause via online portals. Consult local advocate for filing.
Kostenlos • Anonym • Experten-Anwälte
Persönliche Rechtshilfe benötigt?
Verbinden Sie sich mit erfahrenen Anwälten in Ihrer Region für persönliche Beratung zu Ihrer spezifischen Situation.
Kostenlos und unverbindlich.