Can I sue a supplier for missed delivery and claim loss of profits under an Indian contract?

في India
آخر تحديث: Jan 22, 2026
We paid 60% advance for raw materials but the supplier delayed delivery by 6 weeks, and we lost two major orders. They are refusing to compensate, saying delays were “unavoidable” without proof. What remedies can we seek and what evidence should we keep?

إجابات المحامين

Taneja Law Office

Taneja Law Office

Jan 22, 2026
أفضل إجابة
OfCourse, you can sue the supplier. Kindly keep the entire case record available for examination prior to submission as proof. The remedies available under law to pursue and claim your losses as also damages. You can share details about the location of the delinquent supplier. We are in Delhi and should be able to help if it involves invoking the jurisdiction of the Court in Delhi/New Delhi. Kindly feel free to ask for clarifications, if any.
Ishan Ganguly

Ishan Ganguly

Jan 22, 2026

1. Legal Remedies Under the Indian Contract Act


​Under Section 73 of the Act, when a contract is broken, the party who suffers is entitled to receive compensation for any loss or damage caused to them.


​Compensatory Damages: You can claim for the direct loss caused by the delay (e.g., if you had to procure materials from elsewhere at a higher price).


​Loss of Profits (Special Damages): You can claim for the two lost orders only if the supplier was aware, at the time of contracting, that such losses were a likely result of a breach. This is known as the rule of "remoteness of damage."


​Refund of Advance: If you choose to terminate the contract due to the breach, you are entitled to a full refund of the 60% advance plus interest.


​Specific Performance: If the raw materials are unique and cannot be sourced elsewhere, a court can compel the supplier to deliver them.


​2. Overcoming the "Unavoidable Delay" Defense


​The supplier's claim of "unavoidable delay" usually refers to a Force Majeure clause.


​The Burden of Proof: In Indian law, the party invoking Force Majeure must prove that the event was beyond their control and prevented performance. Mere difficulty or "unavoidability" without documented proof (like a government strike, natural disaster, etc.) is not a valid legal excuse.


​Time is of the Essence: If your contract stated that delivery time was "of the essence," any delay gives you the immediate right to void the contract and seek damages.


​3. Essential Evidence to Collect


​To build a robust case, you should preserve the following:


​The Contract/Purchase Order: Specifically sections detailing delivery timelines, penalty clauses for delays, and "time is of the essence" mentions.


​Proof of Communication: Emails or letters where you notified the supplier of the urgency and the potential loss of specific orders if they failed to deliver.


​Evidence of Lost Orders: Documents showing the cancellation of the two major orders and the projected profit margins from those deals.


​Demand Notice: A formal legal notice sent by an attorney demanding delivery or compensation. This is often a mandatory precursor to litigation in India.


​Recommended Next Steps


​Issue a Legal Notice: Have an attorney draft a formal notice demanding the immediate delivery of goods or a refund of the 60% advance with interest and damages for loss of profit.


​Review the Force Majeure Clause: Check your written agreement to see how "unavoidable delays" are defined.


 


 

اطرح سؤالاً مجانياً

مجاني • مجهول • محامون خبراء

هل تحتاج مساعدة قانونية شخصية؟

تواصل مع محامين ذوي خبرة في منطقتك للحصول على نصيحة مخصصة لوضعك الخاص.

بدون التزام. خدمة مجانية 100%.

خبراء قانونيون ذوو صلة

احصل على مساعدة مخصصة من محامين متخصصين في هذا المجال

منذ 2020
محامون 100
البنوك والتمويل الأعمال الشركات والتجارة +1 المزيد
منذ 1909
محامون 75
البنوك والتمويل القضايا والدعاوى الأعمال +1 المزيد

جميع المحامين محترفون معتمدون ومرخصون بسجل حافل مثبت