We are contractor and working for railways, preparing bed (earthen bed ) for laying railway track ( doubling of track ), for this soil was required and NWR deputy chief engineer wrote to DM tonk for approval under central govt's amrit sarovar scheme from
Respostas de Advogados
Quartz Legal Associates
Steps to follow: First, immediately submit a written representation to the District Magistrate, Tonk, enclosing all approvals and seeking release of vehicles and restraint orders against further interference. Second, place the matter on record with the Railway authorities, requesting their intervention as the work pertains to a Central Government project. Third, if vehicles are not released forthwith, file a writ petition under Article 226 before the Rajasthan High Court seeking quashing of the illegal action, release of vehicles, and protection from harassment. Fourth, record all actions taken by the SDM/Tehsildar in writing and under protest, and preserve all documents and evidence for legal proceedings.
Gratuito • Anónimo • Advogados Especialistas
Precisa de Ajuda Jurídica Pessoal?
Conecte-se com advogados experientes na sua área para aconselhamento personalizado sobre a sua situação específica.
Gratuito e sem compromisso.